Construction Work for Memorial Elementary

The construction bond work is scheduled to begin June 23, 2017 and is projected to be completed in August.

Memorial will be completely closed from June 23 to August 16. Administrative offices will relocate to Buel Elementary during the closure. 

Memorial students will attend summer school at Buel, July 31 through August 18, from 8:45 a.m. - 12:15 p.m., Monday through Thursday.

Incoming Memorial kindergartners will attend Kindergarten Transition Camp at Buel, which runs August 22 - 24 from 8:30 - 11:30 a.m.


Proposed bond construction work
includes

  • Seismic upgrades
  • Sewer line replacement
  • Galvanized water line replacement
  • Roofing replacement
  • HVAC unit above library replacement
  • Egress coverage installation

For more details about the bond, click here.

Project Team

Casey Cunningham, Project Manager
  Cornerstone Management
Architect:  Paul Bentley
General contractor:  TBA