Construction Work for Patton Middle School

The construction bond work is scheduled to begin June 23, 2017 and is projected to be completed in August.

The building will be completely closed from June 23 to August 25. Administrative offices will relocate to McMinnville High School during the closure. The Patton office phone,  503.565.4500, will be forwarded to the temporary office at the high school. 

Summer meals program will be consolidated at other schools because of construction. More details here.


Patton students will attend sixth - eighth grade Summer School at Duniway, July 31 through August 17, from 8:30 a.m until noon, Monday through Thursday. The Extended School Year program will also run at Duniway, from August 7 - 17.

Proposed bond construction work includes replacement of roof, HVAC, windows, hallway wainscoting and exterior doors; upgrade of electrical system; new lockers installation; elevator renovation; selected restroom remodeling; interior painting; cafeteria upgrades; and entry lighting installation.

For more details about the bond, click here. Notice of upcoming work. 

Project Team

John Abel, Project Manager
  Cornerstone Management
Architect:  Opsis
General contractor:  Par Tech Construction